JAKARTA, KOMPAS.com – PT Waskita Toll Road as a toll road business entities (BUJT) Cimanggis Cibitung-targeting land acquisition for the toll road was completed in June 2017.
In April 2016 ago, the land acquisition had just one percent. It is fairly slow because basically construction already started back in October 2015 after the stalled four years.
Budget constraints and also the refusal of residents in housing Rafles Hills because it did not want the environment through which the motorway into a bit of constraints that confront PT Waskita Toll Road.
Nevertheless, the problems were gradually solved including denial of citizens who then process dikonsinyasikan state court.
as for the budget of land acquisition, Pt Waskita Toll Road have received assistance through funds bailout BUJT be returned in the scheme of the Institute of Asset Management State (Faith).
“Until now, land acquisition Toll Cimanggis-Cibitung still 4 percent. there will be a special meeting to discuss it to accelerate. We are targeting June next year ( 2017) is 100 percent of its land, “said President Director of PT Waskita Toll Road Herwidiakto, when met at the Ministry of Public Works and Public Housing (PUPR), Monday (12/05/2016).
He is optimistic that the target could achieved because bailouts are now ready and consigned to the Housing Rafles Hills also was settled.
the consequences of delay in land acquisition is made operational Cimanggis-Cibitung toll would be too late one year from the original schedule in 2018 to 2019.
project along the 26.3 kilometer toll road is believed to be able to break up the density of traffic on Jalan Transyogie, Cullinan.
BPN Bekasi regency of Bekasi District Land Agency chief Dirwan Dachri (left, wearing uniforms) explain to citizens Cijengkol, District Setu, Bekasi, on the fair value of the locker Appraisal project Cimanggis-Cibitung toll road on Friday (05/08/2016).
In addition, as a complementary network of toll roads Jabodetabek, Tol Cimanggis-Cibitung also expected to break up the density of the two toll capitals, namely Jakarta-Cikampek Toll Road and Highways jagorawi.
During this crossers of the Jakarta-Cikampek Toll road who wish to Cibubur, Depok, and Bogor must rotate advance through JORR new to Highway Jagorawai towards Bogor.
With the Toll road Cimanggis-Cibitung this then passer road from Cikampek can directly deflecting the vehicle entered the toll road and meet the toll Road jagorawi in Cimanggis.
Under the development plan, the toll Road Cimanggis-Cibitung will be connected with a number of other toll.
First, in Simpang Susun Cimanggis, tolls it will connect with Highway jagorawi and Highways Cinere-jagorawi which is currently still under construction.
Then the second in Simpang Susun Cibitung, will be connected with the Jakarta-Cikampek Toll Road and Highway Cibitung-Cilincing.