JAKARTA, KOMPAS.com – PT Wijaya Karya (Persero) Tbk, or Wika known to win the job of Development Projects Light Rail Transit (LRT) Corridor 1 (Phase 1) Kelapa Gading or Rawamangun Velodrome and Depo LRT Jakarta in Kelapa Gading, North Jakarta , in June.
Wika also has obtained Letter to Proceed (SPMK). According to Director of Operations 1 Wika Gandhira Velasquez, project review process is quite time consuming.
“Required, the project was completed before the Games precisely August 18, 2018,” said Gandhira during a press conference at the House of Wika, Jakarta, Thursday ( 22.12.2016).
To achieve the target, Wika prepare some supporting documents related to the steps that must be done.
Gandhira explained, the target before the Games have meant not work structure complete, but the LRT should have been in operation.
“Because the operation it takes trial usually two months, we must finish the construction it was May,” said Gandhira.
By the count calendar and construction, it is still possible.
Therefore, Wika construction along the 6 kilometers divide into 6 sub-sections. This method never proved successful on the overpass Trans Jakarta route Kapten Tendean-Blok M-Ciledug.
“Busway was 10 kilometers, carried out by sub-contractors with an average of 1 kilometer. We are working in 14 months , “said Gandhira.
taking the example of these, he is optimistic that technically LRT Kelapa Gading-finished Velodrome on target.