UNGARAN, KOMPAS.com – Semarang-Solo toll road Section III Bawen-Salatiga projected to be fully operational in March 2017.
Director of Engineering and Operations PT Trans Marga Central Java (TMJ), Ali Zainal Abidin said, at the beginning of February 2017 it began to carry out a due diligence Ruas Bawen-Salatiga.
Ali estimated the trial will last for one month. “If appropriate, can be operated immediately. If the picture, we expect to be inaugurated in March 2017,” said Ali, Tuesday (12/06/2016) afternoon
Currently the physical progress of the toll roads throughout 17.6 the kilometer has reached about 75 percent. The target, the entire physical work completed by the end of January 2017.
Therefore, concreting and compaction work the land, while completing the accelerated installation of bore pile on unstable soil in point KM 0 Bawen, Kandangan Village, District Tuntang.
in this area at least 2,110 drill points mounted on the left and right expressway with a depth of 43 meters.
“the goal is to strengthen the soil conditions,” he explained.
In addition, the bridge construction Tuntang along 330 meters, cross road Kandangan Village and Village Delik, sub Tuntang, as well as roads in the village of Ujung-End District of Pabelan also accelerated.
Constraints rain
toll Semarang-Solo Section III Bawen-Salatiga recognized delayed from the initial target, which should have been in operation since November 2016 ago.
According to Ali, the weather became one of the main obstacles delayed physical work this toll. Even if the modified target being December else, do not be overtaken.
“If from the material, equipment, up to the human resources (HR) is no problem. We’ve been regular overtime until early morning. But if natural factors, we can not do much, “he concluded.