Nindya work Optimistic Can Accelerate Dam Napun Gete


JAKARTA, KOMPAS.com – Nindya PT Karya (Persero) Tbk selected as service providers Napun Gete Dam construction in Sikka regency, East Nusa Tenggara (NTT). The building contract is valued at USD 849.9 billion.

The contract has been signed with the Government Nindya party, on Wednesday (12/07/2016), the Office of the Directorate General of Water Resources (SDA) Ministry PUPR, Jakarta. This is a multi-year contract with the processing time for five years.

Previously, Nindya work is also designated as the winning bidder at NTT Rotiklot dam construction along with PT Universal Suryaprima. However, unlike in Dam Rotiklot which is a joint operation (KSO) with other companies, in Napun Gete Nindya work is only itself.

“We feel they have the basic capability to undertake the construction of the dam itself so we are confident to forward alone and akhinya through an auction process and the selection we were elected, “said President Director of PT Nindya Karya (Persero) Tbk, Indradjaja Manopol.

Meanwhile, related processing time, the Director General of Water Resources Ministry PUPR Imam Santoso has asked Nindya work speed up the process of construction of Dams Napun Gete order to operate faster than the original plan.

“I always remind friends contractor to spur accelerate progress. Normally 5 years, but this time, so three years alone,” he said.

In response, Indradjaja admitted that his side are confident and able to accelerate the development Napun Gete. He admitted Nindya work of experts in water infrastructure development.

Related accelerated development time, according to him, everything will depend on the acquisition of land. Until now, only 24 hectares are exempted from the total demand reached 161 hectares.

“We do not know who liberated part. But, if it were released at the site of dams and access roads, we can start. if not, such as only access are released, then we can not get up construction, “said Indradjaja.

Nindya PT Karya (Persero) Tbk itself now has started construction. That’s because according to the schedule, the President Joko Widodo (Jokowi) will be a groundbreaking ceremony Dam Napun Gete on 12 or December 13, 2016 or the next week.

– ADVERTISEMENT –

properti.kompas .com

Sign up here with your email address to receive updates from this blog in your inbox.

0 Response to "Nindya work Optimistic Can Accelerate Dam Napun Gete"

Post a Comment