Land Acquisition Pejagan-Semarang toll continues to speed up


JAKARTA, KOMPAS.com – large-scale infrastructure development by the government had to land acquisition.

To overcome this problem, in May, the Minister of Public Works and Public Housing (PUPR) issued a regulation (Candy) on procedures for the use of the bailout fund for land acquisition of business entities motorway.

at this time, the government expects to spend the ground until the end of December 2016 amounted to Rp 16 trillion.

“Remaining time of 1.5 months These targets eg the Trans Java Toll Pejagan to Semarang only Rp 8.7 trillion. It should be pursued finish this land until the end of December 2016, “said the Director of Highways, Urban and Regional Roads Facilitation, Subagiono at the Ministry PUPR, Jakarta, Friday (11/18/2016).

Subagio admit, before the disbursement of the bailout will take time until the billing reached Rp 7.4 trillion. That is, with a target of Rp 16 trillion, there are still remaining Rp 8.6 trillion to be absorbed.

The land acquisition was delayed at the beginning of the year, because the new bailout fund be available in June, although May had been issued Candy.

“It’s a process. Acquisition of land ranging from inventory,” said Subagio.

the next process is the announcement regarding the objections of those whose land will be purchased for the construction of toll roads. Furthermore, the funds disbursement process includes appraisal, consultation and validation.

“The length of the process, so that Rp 7.4 trillion has been outstanding in the period June to October. That means one month to Rp 2 trillion,” said Subagio.

He added that the bailout is made the assurance in the field, both for the National Land Agency and the community. Thus, the land acquisition process could be faster.

– ADVERTISEMENT –

properti.kompas.com

Sign up here with your email address to receive updates from this blog in your inbox.

0 Response to "Land Acquisition Pejagan-Semarang toll continues to speed up"

Post a Comment