Every Sunday, the Jakarta MRT Work Reveals Significant Advances


JAKARTA, KOMPAS.com – Entering the last week of November 2016, the rail-based infrastructure works, the Mass Rapid Transit (MRT) Jakarta increasingly displaying significant developments.

In the area of ​​Upper Hamlet Station, for example, the ongoing three jobs done by operation (KSO) between Sumitomo Mitsui Construction Company with PT Hutama Karya (Persero) or SMCC-HK.

the third job is a first, tunneling MRT underground station Hotel Indonesia roundabout towards Hamlet station on the whole 1.1176 meters.

Bor Mustikabumi I have departed from the upper Hamlet station and is being carried out excavation for tunneling underground line MRT to the station Setiabudi.

There is no Drill Mustikabumi II has been digging tunnels along 732 meters.

Currently Drill Mustikabumi II has departed from Dukuh Atas station and is being carried out excavation for tunneling underground line towards station MRT Setiabudi.

The second job is on the north side backfill Dukuh Atas station, and the third work in the form of reinforcement assembly of ventilation shafts at Dukuh Atas station.

KOMPAS.com / ANDREW GARRY Lotulung Activities project worker has completed the drilling of the tunnel for rapid mass transport (mass rapid Transit / MRT) station Dukuh Atas, Central Jakarta, Thursday (24/11/2016). The first phase of the MRT project is expected to be completed by 2018.

Jakarta MRT project segment Dukuh Atas station has started since 1 September 2015 and is planned to be finished on December 31, 2016.

While in the station area roundabout Hotel Indonesia, the ongoing four job with a contractor that is equal to the segment Upper Hamlet station namely SMCC-HK.

each of these jobs are plestering walls, installation of ducting for ventilation, work backfilling on the north side, and reinforcement assembly room on the platform area.

following the progress of work of MRT Jakarta Dukuh Atas station segment recorded photographer Kompas.com:

KOMPAS.com / ANDREW GARRY Lotulung Activities worker has completed drilling the tunnel project to mass rapid transit (mass rapid Transit / MRT) station Dukuh Atas, Central Jakarta, Thursday (24/11/2016). The first phase of the MRT project is expected to be completed by 2018.

KOMPAS.com / ANDREW GARRY Lotulung Activities worker has completed drilling the tunnel project for mass rapid transit (Mass Rapid Transit / MRT) Station Dukuh Atas in Central Jakarta Thursday (11/24/2016). The first phase of the MRT project is expected to be completed by 2018.

KOMPAS.com / ANDREW GARRY Lotulung Activities worker has completed drilling the tunnel project for mass rapid transit (Mass Rapid Transit / MRT) Station Dukuh Atas in Central Jakarta Thursday (11/24/2016). The first phase of the MRT project is expected to be completed by 2018.

KOMPAS.com / ANDREW GARRY Lotulung Activities worker has completed drilling the tunnel project for mass rapid transit (Mass Rapid Transit / MRT) Station Dukuh Atas in Central Jakarta Thursday (11/24/2016). The first phase of the MRT project is expected to be completed by 2018.