JAKARTA, KOMPAS.com – Minister of Public Works and Public Housing (PUPR) Basuki Hadimuljono reiterated throughout the infrastructure construction work XVIII 2018 Asian Games will be completed on time as planned, ie November 2017 with the standard quality Olympic Council of Asia (OCA).
Therefore, the acceleration continues to do so as the targets are missed and remain in accordance with a predetermined schedule.
“We have ordered the contractor to perform work time 3 shifts per day for 7 days. in addition, contractors are also required to use an efficient working method, “Basuki said in a press release received Kompas.com, Wednesday (12/14/2016).
Basuki also added the Asian Games infrastructure is ready for the test match which will be held before the main match of the Asian Games was held.
Meanwhile, related to the progress of construction, Basuki convey the average progress of construction work 11 sports venues per December 14, 2016 has reached 12 percent.
Ke -11 venues namely the Main Stadium, Swimming Stadium, Field Hockey, Football Field A / B / C, Archery, Tennis Stadium, and Istora.
As is known, the construction or rehabilitation work execution venue is divided into seven packages that GBK AG 1 (Main Stadium), AG 2 (Training Facility), AG 3 (Swimming Stadium), AG 4 (Field Hockey, Archery and Football Field A / B / C).
Then AG 5 (Istora ), AG 6 (Stadium Tennis Indoor and CenterCourt), and AG 7 (Stadion Madya Stadium, Softball, Baseball and the House Basket).
in addition to the venue of Asian Games, positive progress was also demonstrated by the construction of Wisma Athletes in Kemayoran .
“Currently, the progress in the plan which is 37 percent of the planned 35 per cent of the total 10 towers built,” added Basuki.
Three towers of flats (flats) built in Block C2 with capacity of 1,932 residential units and seven towers in Block D10 by the number of 5,494 housing units.
Each unit has an area of 36 square meters which can be occupied by three people. At Block D10 also has a dining room with a capacity of 2,500 people.
As for the construction of towers Jakabaring, Palembang is targeted for completion in December 2016.
Currently, five towers were built, of which two towers is still under development by the Ministry PUPR. While three other tower was finished in 2015 ago.