JAKARTA, KOMPAS.com – Based assignment through Presidential Decree (Decree) No. 100 of 2014, PT Hutama Karya (Persero) designated to build 4 Toll Trans Sumatra.
Because incoming priority projects, 4 roads this toll road is planned to operate in 2019. However, there are some sections of the sections that can be opened from next year.
Here’s his review.
1. Bakauheni-Terbanggi Large
In this section, the section is targeted to operate in 2017 is the start of the Port-Interchange (IC) Bakauheni.
The soil is targeted to the free end of this year. While construction is scheduled for completion in March 2017 and operational in July 2017.
The next section is the Bakauheni-Interchange Interchange Trump. With the target of land and construction are non-December this year, targeted operations in April 2017.
Then, IC-IC Sidomulyo Trump also targeted to be operational in 2017, ie in August. Target land acquisition is December this year.
If the target is reached, the construction is expected to be completed in June 2017.
Another section will operate in 2017 in the section of the Bakauheni-Terbanggi is IC Lematang- IC Kotabaru.
Currently, the soil is 100 percent free. As for the construction expected to be completed later this year and operating in March 2017.
Still in this section, section IC Metro-IC Mount Sugih expected to operate in June 2017, with the construction plan was completed in March 2017.
Finally, the section is expected to be commissioned next year Branti IC-IC Metro with a target construction in March 2017. While the operation is planned to take place in June 2017.
2. Medan-Binjai
This section is only divided into three sections, namely Tanjung Mulia-Helvetia, Helvetia-Semayang, and Semayang-Binjai. Total targeted to be operational next year.
Section 1 with a length of 6.27 kilometers, Tanjung Mulia-Helvetia expected to be operational in December 2017.
For land acquisition is targeted to the end of this year, while construction is expected to be completed in October next year.
Section 2 with a length of 6.175 kilometers, Helvetia-Semayang targeted to be operational in February next year. Before that, Hutama construction work scheduled for completion in December this year.
With a length of 4,275 kilometers, Section 3 to the Semayang-Binjai expected to be commissioned in 2017. Same with section 2, the construction is targeted to be completed later this year.
3. Palembang-Simpang Indralaya
Like the Medan-Binjai, this segment also consists of three sections with a total length. This segment is also expected to start operating next year.
In section 1, Palembang-Pamulutan is targeted to be operational in February 2017. Later this year, the road construction is already planned to be completed.
Section 2 , plans Pemulutan-operated KTM August 2017. previously, construction was completed in June 2017.
While in the third section, the KTM-Indralaya in the construction process until June 2017. If achieved, this section could dilangsukan operational in August 2017 .