KUPANG, KOMPAS.com – Construction of Dams Raknamo located in the village Raknamo, District Amabi Oefeto, Kupang, East Nusa Tenggara (NTT), is currently showing positive deviation.

As of early November 2016, the progress of the construction of this dam has reached 74.6 percent.

Committing Officer (CO) Dam I, Central River Region II Nusa Tenggara, Davianto Frangky B Welkis, say, the main work is being done that drains dodger (conduit and tunnel) and the body of the dam (checkers).

Jobs was the other main dam saddle (saddle dam), spillway (spill way), access roads and bridges, as well as inspection road around the pond area.

“for the development of the construction of dams Raknamo until Sunday (06/11/2016) realization is already 74.6 percent. We are targeting the end of 2016 can already be reached 80.16 percent and if you see these conditions, it is estimated by 2017 all are finished, “said Frangky to Kompas.com, Tuesday (11/08/2016).

Frangky admitted, to monitor and evaluate the process of dam projects Raknamo, it was with a team of consultants and a team of operators is always coordination and discussion every day.

in fact, coordination is also well established between the provincial and local governments and related ministries and contractor.

it was intended that the technical problems encountered in the field could be overcome and find a way out, so that the project can be completed on time and can be utilized for the benefit of society.

for the year further Frangky 2016, the funds allocated for the construction of Rp 55 billion. This fund has been depleted and absorbed since January 2016.

Kompas.com/Sigiranus Marutho Bere President Joko Widodo directly review Raknamo dam building, in the district of Kupang, East Nusa Tenggara (NTT), Saturday (07/25/2015 )

According Frangky, the company currently owes Rp 205 billion to the contractor PT Waskita Karya (Persero) Tbk. Even so, he is impressed by the commitment of the state-owned enterprises are still working, although the government owes hundreds of billions of rupiah.

“The debt will be paid off and it certainly would be a matter between the Ministry and the Ministry of Finance PUPR. The point today we focus so that this work can be immediately completed in accordance with the target, “said Franky.

Subsequently, after the dam was completed, it will not necessarily be directly used, because they must be examined again by a team of commission dam safety.

They will check in detail to ascertain whether the dam is already qualified or not. If anything less would be solved.

“If all the conditions are met then it will soon be filled. However, the dam will be directly used, because they still have to be checked again mode of operation. After that, a new certificate for the operation was given and that means it could be flooded, “he said.

to note, laying the first stone dam Raknamo by President Joko Widodo on December 20, 2014 last.

Dam area of ​​147 hectares, which was built with funds of Rp 760 billion a capacity of 14.09 million cubic meters capacity.

the function of this dam is as clean water supply for the capital city of Kupang 100 liters per second.