JAKARTA, KOMPAS.com – Construction of rail-based transportation infrastructure, Mass Rapid Transit (MRT) Jakarta increasingly show significant progress.
Special to the working area of Lower Dam Station, there are three work being done by the joint venture Shimizu-Obayashi -Wijaya works Jaya Construction (SOWJ) as a contractor.
the third job is the first installation of OTE Duct on the East side, and the preparation of foundry Platform Lower Dam station.
Then, a second job is preparation for re-release (relaunching) tunnel boring machine or TBM 2 (Antareja II) towards Setiabudi.
Currently, TBM 2 is located in the departure area TBM-level platform stations Bendungan Hilir.
The third work is the preparation of drilling through station Setiabudi after TBM 1 (Antareja I) has been completed through the process passthrough.
the total length of the tunnel (tunnel) that has been done by the TBM 1 and TBM 2 from region Pemuda Statue to Bendungan Hilir each -masing namely along the 2,040 meters.
following its development:
KOMPAS.COM/GARRY ANDREW Lotulung Activities worker has completed drilling the tunnel project for mass rapid transit (mass rapid Transit / MRT) station neighborhood Bendungan Hilir, Central Jakarta, Thursday (03/11/2016). The first phase of the MRT project is expected to be completed by 2018.
KOMPAS.COM/GARRY ANDREW Lotulung Activities worker has completed drilling the tunnel project for mass rapid transit (Mass Rapid Transit / MRT) Station neighborhood Bendungan Hilir, Jakarta center, Thursday (03/11/2016). The first phase of the MRT project is expected to be completed by 2018.
KOMPAS.COM/GARRY ANDREW Lotulung Activities worker has completed drilling the tunnel project for mass rapid transit (Mass Rapid Transit / MRT) Station neighborhood Bendungan Hilir, Jakarta center, Thursday (03/11/2016). The first phase of the MRT project is expected to be completed by 2018.
KOMPAS.COM/GARRY ANDREW Lotulung Activities worker has completed drilling the tunnel project for mass rapid transit (Mass Rapid Transit / MRT) Station neighborhood Bendungan Hilir, Jakarta center, Thursday (03/11/2016). The first phase of the MRT project is expected to be completed by 2018.