2018, from Balikpapan to Samarinda Cus Can Jump!


Toll Road Project Balikpapan-Samarinda targeted for completion in 2018. Photo: Rumah123 / Ministry PUPR

The motorway linking the city of Balikpapan to Samarinda being actively worked on. The construction project is carried out simultaneously with a target for completion in 2018.

With the 99.2 kilometer road length, the total investment value of this toll jaln 6 trillion.

“I think progress is good, Mr. Governor also active in the liberation of this land. So, I think our target in 2018, hopefully, “said Minister of Public Works and Public Housing (PUPR), Basuki Hadimuljono, while reviewing this project, Friday (4/11).

Read also: Come on, Reaches rating Green Street!

Currently, the rest of the land acquisition is still about 17 percent with a target to be completed in December this year. The rest of the funding problems of land acquisition will be financed by bailout Toll Road Agency (BUJT).

Toll Road Project Balikpapan-Samarinda This process consists of 5 sections. With details, Section I: along 22.03 kilometers from Balikpapan Km 13 to Samboja. Section II: 30.98 km from Samboja-Muara Jawa. Section III: 17.3 km from Muara Jawa-Palaran. Section IV: 17,95 km from Palaran-Samarinda and Section V: 11.09 km.

Many funders construction of this highway. Section I and Section V financed by central and local governments. Section II, III, and IV undertaken by the investor PT Jasamarga Balikpapan Samarinda. (Wit)